Now anticipated cost overrun of delayed central sector projects in the coal sector

Annual · INR billion · 1995–2024 · Published by India — Reserve Bank of India

Latest · 2024

290.57 INR billion

down −40.5279 INR billion vs 2023

Ten-year high
725.21 INR billion · 2021
Ten-year low
190.22 INR billion · 2017

INR billion

Use this series in your AI

Use FactIQ to chart rbi::rbi|0232143f250fe988 over the last ten years, with its latest value and the change over the past year.

Paste into an AI model with FactIQ connected. How to connect

About this series

This series tracks the currently anticipated cost overruns for delayed central sector projects specifically within the coal industry. The data is part of the industrial statistics provided by the Reserve Bank of India and reflects the total additional expenditure expected beyond the original budget for these government-led initiatives. (Footnote: Notes : 1. Data relate to central sector projects costing Rupees 100 crore and above up to 2010. From 2011 onwards data pertain to projects costing Rupees 150 crore and above. 2. Projects without date of commissioning are not considered. 3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'. 4.Surface transport = Road transport + Shipping & ports. 5.Others = Heavy Industry+ Defence Production + Health & family welfare + Urban Development. Source : Ministry of Statistics and Programme Implementation, Government of India.)

Series ID
rbi::rbi|0232143f250fe988
Frequency
Annual
Units
INR billion
Coverage
1995 – 2024
Now anticipated cost overrun of delayed central sector projects in the coal sector: 290.57 INR billion for 2024 · FactIQ